Well, we're thinking we may be in the home stretch of our garage construction project, but who knows, so we are keeping our fingers crossed. It's been quite a difficult time, requiring lots of patience and perseverance, but it's definitely going to be worth it in the end. Three different contractors told us this was a 3 month project, so then you expect to have to double that, but now we've gone triple!! Please just let it all end so we have a little time to relax before the baby arrives! Here are some pictures from all the stages along the way.
![]() |
| August 7, 2012 - We broke ground at the beginning of August. Cut down some trees, ripped out the driveway, took off the front porch roof, and dug a huge ditch for the sewer and foundation work. |
![]() |
| September 7, 2012 - Excavation and sewer work complete, foundation and slab poured. |
![]() |
| Garage Slab and foundation. |
![]() |
| September 26, 2012 - Framing of first floor. |
![]() |
| Had to have a crane to lift the huge beam at the front of the garage, as well as another one in the middle. |
![]() |
| Framing on the back side. |
![]() |
| October 5, 2012 - Finished the ceiling of the garage level, so able to start framing on the second floor. |
![]() |
| Josh and Chaz looking inside the garage and standing on the freshly poured driveway. |
| More views of the framing inside the garage. |
| October 11, 2012 - Taking in the views from the second floor before it had walls. |
| Going to have a nice view of the creek from our new bathroom. |
![]() |
| October 16, 2012 - Starting to put up some exterior walls. |
![]() |
| October 21, 2012 - Turns out you build second floor walls on the ground and then hoist them upright with a mast and pulley. |
| And "ta dah", we have a wall! |
![]() |
| October 23, 2012 - A little early season snow storm put a bit of a damper on our warm construction days. |
| It snowed in our bedroom and Josh had to shovel it all out! |
![]() |
| November 6, 2012 - Roof is starting to go up. |
![]() |
| November 8, 2012 - The new entry is closed in, but doesn't have a waterproof roof...tarp time! |
| Ceiling in the new entry that needs to be protected from water. |
| Here you can see how the new entry was just attached to the old front of the house. |
| December 23, 2012 - We got dumped on in December! The wall were all closed in at least, but still no roof on there, just plastic! Talk about stressful. |
| Did I mention that this was the end of 4 months, and we still aren't even remotely close to being finished? |
![]() |
| January 6, 2013 - We finally had enough clear days in a row that the roofers were able to get in and shovel off all the snow and put on a real roof. Thanks goodness! |
![]() |
| Me, 4 months pregnant, climbing to the top of our 3 story A-Frame to remove all the snow from the roof so we could install a vent for the range hood. |
![]() |
| My billy goat path up the roof as I removed snow on the way. Long way down! |
![]() |
| January 16, 2013 - Finally got the windows installed! |
![]() |
| And the pre-stained siding is starting to go up too. |
![]() |
| January 18, 2013 - Interior wall framing is starting to come together. |
![]() |
| Front wall of our bedroom. |
![]() |
| Street wall of our bedroom. |
![]() |
| A peek into the new bathroom. |
![]() |
| The roof took a really long time to build because of all the complicated peaks and dormers that had to come together at all different levels. |
![]() |
| January 23, 2013 - More of the exterior siding detail starting to come together. |
![]() |
| January 26, 2013 - I spent hours and hours this weekend hacking and scraping away the 4 inch layer of ice and was able to reclaim our driveway! |
![]() |
| February 6, 2013 - Finally ready to get the insulation installed! |
| Inside the new garage...should stay nice and toasty in here! |
| Furnace and water heater stand. |
![]() |
| Our bedroom. |
![]() |
| Bathroom and future location of the vanity and sink. |
![]() |
| Bathtub and door to the balcony. |
![]() |
| February 10, 2013 - Seemed like the pace was starting to pick up for awhile...lots of noticeable changes each day. Drywall is up now. |
![]() |
| Hallway leading to the upstairs room. Entrance to garage is on the right. |
![]() |
| It's really going to be an awesome garage. |
![]() |
| Stairs up to our bedroom and the extra tall doorway! |
![]() |
| Did I mention that it has now been over 6 months, more than double the amount of time that 3 different contractors said it would take to build this thing, and we are still not close to being done?! |
![]() |
| April 7, 2013 - The inside is almost all done and ready for inspection, if we can ever qualify for final inspection. |
![]() |
| Paint, trim, carpet, electrical, plumbing...it's all looking good! |
![]() |
| Can't wait to fill up this walk-in closet! |
![]() |
| Loving the new granite and tile in the bathroom. |
![]() |
| Hoping we'll get to bath in this monster soaker tub soon! |
![]() |
| The water closet, specially designed for the needs of my man. |
| April 10, 2013 - Josh's new car in front of his new garage. |
| Loving our fancy new garage door! Almost done now, hopefully we'll be able to say everything in final final by the end of the month of April...9 months later!!! |